ERP Master Data Change Request

Master data change from request to validation in any ERP system

ERP Systems
Sign Up to Use

Lead Time

111.4h

Cycle Time

2.4h

Wait Time

109.0h

PCE

2.1%

Stages

7

Bottleneck

Approval (1-2 levels)

Value-Add vs Non-Value-Add

Value-Add (VA)

An activity is value-add if it meets all three criteria:

  • The customer is willing to pay for it
  • It transforms the product or service
  • It is done right the first time

Examples: Assembly, diagnosis, treatment, coding, machining, testing

Non-Value-Add (NVA)

Activities that consume time or resources but don't add value from the customer's perspective:

  • Waiting — queues, approvals, batching delays
  • Transport — moving materials or information
  • Motion — unnecessary movement of people
  • Rework — correcting defects or errors
  • Over-processing — doing more than required

Note: Some NVA is necessary (compliance, safety). Target unnecessary NVA first.

Process Timeline

Value-Add vs Non-Value-Add

Bottleneck Analysis

Stage Efficiency

# Stage Cycle (h) Wait (h) VA Resource Defect % Efficiency
1 Change Request Submitted 0.25 0.0 VA Business User 20.0% 100.0%
2 Data Steward Review 0.5 24.0 VA Data Steward 10.0% 2.0%
3 Impact Assessment 1.0 24.0 VA Data Steward 8.0% 4.0%
4 Approval (1-2 levels) 0.1 48.0 NVA Approver 3.0% 0.2%
5 Change Execution in System 0.25 8.0 VA Data Admin 5.0% 3.0%
6 Validation & QA Check 0.25 4.0 VA Data Steward 6.0% 5.9%
7 Requestor Notification 0.05 1.0 VA System 1.0% 4.8%